International airport "Lviv" - the reconstruction of the new passenger terminal

7 êâiòíÿ 2008  |  Äåïàðòàìåíò ðîçâèòêó òà êîîðäèíàö³¿ ñèñòåì òðàíñïîðòó òà çâ'ÿçêó

INVESTMENT PROJECT REVUE

Name of project

The reconstruction of  the new passenger terminal

Characteristics of enterprise (organization)

 

Requisites of enterprise (organization):

The State Enterprise “International airport “Lviv”.  Lviv, 168 Lubinska street, the airport of Civil Aviation. Account No 26009070290 MFO 325956, EDRPOY 33073442 in Lviv Branch of Express Bank. The Certificate about state registration Serial No AOO No 373879 dated 19.07.04.

Postal address

The State Enterprise “International airport “Lviv”   Lviv 79000,
168 Lubinska street, the airport of Civil Aviation

Phone, fax

Telephone (032) 298316    Fax (032) 298025  

Property form
Organizational and legal form
State property share (%)

state

Unitary commercial enterprise

100%

Director of enterprise (organization):

 

Title

The general director of the State Enterprise “International airport “Lviv”

Name, patronymic, surname

Olexander Yukhymovych Zahreva

Main products of enterprise

The providing of the airport handling

Statutory fund of enterprise (thousand USD)

2144 US dollars

Number of employees

620

Main production turnover per year (thousand USD)

8476,7 US dollars

Characteristics of the project

Aim of project

The increase of the passenger capacity of the airport, upgrading the handling of passengers and upgrading them up to the proper ICAO standards.

Main tasks of project to be solved during project implementation

1.       square -  34 thous. sq/ì.;
2.       passenger capacity - 1000 pax./hour;
3.       Start of works – October 2008
4.       Finish of works – December 2010

List of expected results

1.       18 check-in desks for passengers;
2.       8 positions for passport control;
3.       4 point for security control;
4.       2 points for baggage claim;

Correspondence of project aims to program of activity of the Cabinet of Ministers of Ukraine

The project meets the requirement of the point 3 of the tasks and events for the preparation and performing  in  Ukraine in the final part of football Europe championship in 2012,  confirmed by State industry program.

Level of readiness of investment project
Availability of technical specifications (FS)

Readiness for the projecting  stage
FS requires the approval with the State Aviation Administration 

Cost of project (expected)

 

Total investment rate, including (thousand USD):

 

   - own funds

-----

   - need in investment funds

90 376,0 US dollars

Internal rate of return (IRR), %

16,07

Financiering sources (MFO)

Investing funds

Means (form) of investment attraction

Concluding of investing agreements

Term of project realization

 

Term of project payback

9,4 years

Procedure of investor selection

The performing of tender with the Ministry of Transport and Communications of Ukraine

Availability of innovative component of project

According to the project, created by the investor

Basis of need of credit resource or cost attraction, specifying reasons why project realization cannot take place at the expense of budget funds

The project meets the requirement of the point 3 of the tasks and events for the preparation and performing  in  Ukraine in the final part of football Europe championship in 2012,  confirmed by State industry program.

Type of loan payback guarantee

Government guarantee

Contact person of investment project:
Title, name, patronymic, surname

The General director of the State Enterprise “International airport “Lviv”
Olexander Yukhymovych Zahreva

Phone, fax

Telephone (032) 298316    Fax (032) 298025  


(ñ) Äåðæàâiààäìiíiñòðàöiÿ, 2001-2008